Progress

Replaced the joist

Dad replaced the joist which where there and added some bricks to support it

Categories
Progress

Removed the rest of slabs

Dad did a phenomenal job removing the rest of slabs on his own on

Categories
Progress

Filled soil by man hole and fitted back bath/sink

Had Tim help to fill the soil up by the manhole. Dad also connected back up the upstairs basin and toilet

Categories
Progress

Fitted the outside watste pipe

Spent the day fitting the outside waste pipe

Categories
Progress

Inspector Approved

The building regulation came round and approved the pipe work which dad as done

Categories
Progress

Moved Bricks

Spend about 1 1/2 hours moving the bricks from the front garden to the back

Categories
Progress

Bricks and Blocks

Needed additional bricks and blocks from the bricklayer

£10.50

Categories
Progress

Foundation bricks laid

The brick layers have just finished laying the bricks for the foundation

Categories
Progress

Bricklayer

The bricklayer came round to look to look at the job – Quoted it be £600

Categories
Progress

Concrete laid on foundation

The concrete has been laid onto the foundation